Be careful! The number of items produced cannot be negative.
Begin by determining the boundary lines of the inequalities.
Let P be the total profit. Make an organized table to write the function and then substitute the vertices of the feasible region into the function.
System:c≥ 0 t≥ 0 3c+2t ≤ 108 0.5c+t ≤ 20
Graph:
Tables and Chairs: 34 chairs and 3 tables
Maximum Profit: $955
We have been given that c is the number of chairs and t is the number of tables that Cal's Carpentry can produce in one day. Since the number of products cannot be negative, we can write the first two inequalities as shown below.
c≥ 0 & (I) t≥ 0 & (II)
Examining the table, two more inequalities can be written.
| Product | Carpentry Time (hr) | Finishing Time (hr) |
|---|---|---|
| chair | 3 | 0.5 |
| table | 2 | 1 |
Using the given data on the table, we will write two inequalities, one for the carpentry time and one for the finishing time. Let's start!
| Carpentry Time | Finishing Time | ||
|---|---|---|---|
| Verbal Expression | Algebraic Expression | Verbal Expression | Algebraic Expression |
| Carpentry time of c number of chairs (hr) | 3 c | Finishing time of c number of chairs (hr) | 0.5 c |
| Carpentry time of t number of tables (hr) | 2 t | Finishing time of t number of tables (hr) | 1 t |
| Total carpentry time is less than or equal to 108 hours. | 3 c+ 2 t≤ 108 | Total finishing time is less than or equal to 20 hours. | 0.5 c+ 1 t≤ 20 |
As a result, we have four inequalities to write a system. c≥ 0 & (I) t≥ 0 & (II) 3c+2t ≤ 108 & (III) 0.5c+t ≤ 20 & (IV)
To graph the inequalities, we should first determine their boundary lines. They can be determined by replacing the inequality symbol with an equality sign. Let's begin with Inequality (I) and Inequality (II).
ccc & &Inequality &Boundary Line & I: &c ≥ 0 &c = 0 & II: &t ≥ 0 &t = 0 Here, c is represented by the horizontal axis and t is represented by the vertical axis. In this case, the boundary lines are the axes and the inequalities represent the Quadrant I. This means that we will shade Quadrant I. Because of the non-strict inequalities, the boundary lines will be solid.
Next, we will graph Inequality (III). Let's first determine its boundary line.
cc
&Inequality III &Boundary Line III
&3c+2t ≤ 108 &3c+2t = 108
The boundary line is in standard form, so it might be a better option to find its intercepts to graph it. We will substitute t= 0 for the x-intercept and c= 0 for the y-intercept.
| 3c+2t=108 | ||
|---|---|---|
| Operation | x-intercept | y-intercept |
| Substitution | 3c+2( 0)=108 | 3( 0)+2t=108 |
| Calculation | c=36 | t=54 |
| Point | (36,0) | (0,54) |
Now we can plot the intercepts and connect them with a line segment. Notice that the number of products cannot be negative, so the line will be bound by the axes. The boundary line will also be solid because of the non-strict inequality.
Next, we will decide which region we should shade by testing the point (0,0).
c= 0, t= 0
Zero Property of Multiplication
Since the point satisfies the inequality, region that contains the point will be shaded. Let's do it!
We will proceed in the same way to graph the last inequality. cc &Inequality IV &Boundary Line IV &0.5c+t ≤ 20 &0.5c+t = 20 Now we will find its intercepts.
| 0.5c+t=20 | ||
|---|---|---|
| Operation | x-intercept | y-intercept |
| Substitution | 0.5c+ 0=20 | 0.5( 0)+t=20 |
| Calculation | c=40 | t=20 |
| Point | (40,0) | (0,20) |
The boundary line passes through the points (40,0) and (0,20). Next, we will test the point (0,0) to decide the region that will be shaded.
c= 0, t= 0
Zero Property of Multiplication
We will again shade the region that contains the test point.
The overlapping section of the graph above represents the feasible region.
We can determine the first three vertices of the feasible region to be (0,0), (0,20), and (36,0) by looking at the graph The fourth vertex is the point of intersection of Boundary Lines (III) and (IV). To find it, we will solve the equations of these lines together. Let's do it!
(II): LHS-0.5c=RHS-0.5c
(I): t= -0.5c+20
The x-coordinate of the point is c=34. With this, we can find its y-coordinate.
(II): c= 34
(II): Multiply
(II): Add terms
The point of intersection is (34,3). From here, we can list the vertices. Vertices (0,0), (0,20), (36,0), (34,3)
Let P be the total profit. We will make an organized table to write a function for the total profit on the products.
| Verbal Expression | Algebraic Expression |
|---|---|
| Profit for c number of chairs ($) | 25 c |
| Profit for t number of tables ($) | 35 t |
| Total profit for the products $P | P= 25 c+ 35 t |
To find the number of chairs and tables that maximize the profit, we will substitute the vertices into the function.
| Vertex | 25c+35t | P |
|---|---|---|
| ( 0, 0) | 25( 0)+35( 0) | $0 |
| ( 0, 20) | 25( 0)+35( 20) | $700 |
| ( 36, 0) | 25( 36)+35( 0) | $900 |
| ( 34, 3) | 25( 34)+35( 3) | $955 |
To maximize the profit, 34 chairs and 3 tables should be made. With this, the maximum profit will be $955.